98-187. General criteria for sediment and erosion control plans.


General criteria for sediment and erosion control plans are as follows:
(1) 
All denuded areas shall be stabilized.
(2) 
All soil stockpiles shall be stabilized.
(3) 
Permanent vegetation shall be established.
(4) 
Adjacent properties shall be protected from sediment from the development.
(5) 
Adjacent properties shall not be subjected to erosion due to increased runoff water from the development.
(6) 
Cut and fill slopes shall be constructed and stabilized in a way to reduce erosion.
(7) 
On-site waterways and outlets shall be stabilized.
(8) 
Storm sewer inlets shall be protected from sediment.
(9) 
If working in or crossing live streams, they shall be protected during construction.
(10) 
Construction access routes shall be stabilized to include dust control.
(11) 
Temporary sediment and erosion control structures shall be removed when the development is finished.
(12) 
Maintenance of stormwater, sediment, and erosion control structures shall be addressed adequately.
Ord. No. 39-1998, § 6.1.6, 12-1-1998